Install the primary backfill in layers

GueteschutzKanalbau-Rohrverlegung-Beton-38.jpg
  • Before each stage of backfilling, pull up the shoring to the required height.
  • Layer by layer, install and compact the backfill, including towards the trench wall.
  • From the covering layer to 1 metre above the top of the pipe, only light- and medium-weight compaction equipment may be used (operating weight of up to 300 kg).

Principles:

  • Use compaction equipment that is appropriate for the layer thickness.
  • Compact in passes running inwards from each trench wall and overlapping in the middle of the trench.
  • As a rule, use at least three passes to compact each layer of backfill.
  • The backfill material must be free of foreign substances/objects (e.g. wood, waste, topsoil).

Install the primary backfill in layers

Schritt 12: Hauptverfüllung lagenweise einbauen, „Schweres Verdichtungsgerät“ (größer 300 kg Dienstgewicht erst ab 1 m über Rohrscheitel einsetzen!
i

Do not use heavy compaction equipment (operating weight of over 300 kg) until the depth of the backfill above the top of the pipe is at least one metre!

9-2-6_1

Install the primary backfill in layers

Schritt 12: Hauptverfüllung lagenweise einbauen, Hauptverfüllung lagenweises verdichten, auch gegen die Grabenwand
i
  • Before each stage of backfilling, pull up the shoring to the required height.
  • Layer by layer, install the primary backfill and compact it in multiple passes, including against the trench wall.
  • The backfill material must be free of foreign substances/objects (e.g. wood, waste, topsoil).
9-4-6_1

Install the primary backfill in layers

Schritt 12: Hauptverfüllung lagenweise einbauen, Hauptverfüllung lagenweises einbringen
  • Before each stage of backfilling, pull up the shoring to the required height.
  • Layer by layer, install the primary backfill and compact it in multiple passes, including against the trench wall.
  • The backfill material must be free of foreign substances/objects (e.g. wood, waste, topsoil).

Install the primary backfill in layers

Schritt 12: Hauptverfüllung lagenweise einbauen, Grobplanum verdichten und auf Tragfähigkeit prüfen
i

Compact the final backfill layer

Check the load-bearing capacity of the final backfill layer

9-xx_Tabelle-ZTV-A
9-6-6_1